14 new AIIMS will be ready by 2025: Health minister

Published On 2021-04-03 09:30 GMT   |   Update On 2021-04-03 09:30 GMT
Advertisement

New Delhi: The Minister of State in the Ministry of Health and Family Welfare, Mr. Ashwini Kumar Choubey recently briefed the upper house about the Status of 22 new AIIMS approved under Pradhan Mantri Swasthya Suraksha Yojana (PMSSY).

The minister was responding to a series of queries relating to the number of All India Institute of Medical Sciences (AIIMS) under construction in the country, the current status of the undergoing projects; and the time period within which these projects are proposed to be completed.

Advertisement

According to the written response of the Minister tabled in Rajya Sabha, out of the 22 AIIMS approved 6 institutes located at Bhopal, Bhubaneswar, Jodhpur, Patna, Raipur and Rishikesh are already functional while the rest 16 AIIMS are at different stages of physical progress.

Eight institutes each at Raebareli, Mangalagiri, Nagpur, Kalyani, Gorakhpur, Bathinda, and Bilaspur are at the later stages of development and expected to come up by the end of 2021.

Furthermore, the institutes approved for Guwahati, Madurai, Deoghar, Rajkot, and Bibinagar are targeting towards completion by the latter half of 2022 while the institutes at Samba and Manethi are expected to complete in the year 2023.

Similarly, Sept 2024  has been set as the date of completion of AIIMS Darbhanga pending handover of 200-acre encumbrance-ree land by the State government.

However, AIIMS Awantipura, approved on 10.01.2019 will be completed by Jan 2025 as only 3% progress has been made in the construction work of the institute.

DETAILS OF NEW AIIMS (16) UNDER PMSSY

S.

No.

Location of

AIIMS under PMSSY

Date of

Cabinet Approval

Approved

Outlay (Rs Cr)

Date for

completion (target)

Physical Progress

1

AIIMS,

Raebareli

05.02.2009

[RCE was approved by EFC on 22.06.2017]

823

March, 2021

  • Residential and OPD block completed.
  • Medical College / Hospital Progress – 98%

2

Mangalagiri, Andhra Pradesh

07.10.2015

1618

June, 2021

  • Progress of construction work:
  • Phase I - OPD Block & Residential Complex: 98%
  • Phase II – Hospital and Academic Campus: 64%

3

Nagpur, Maharashtra

07.10.2015

1577

June, 2021

  • Progress of construction work:
  • Phase I - OPD Block & Residential Complex: 100%
  • Phase II – Hospital and Academic Campus: 86%

4

Kalyani, West Bengal

07.10.2015

1754

June, 2021

  • Progress of construction work:
  • Phase I - OPD Block & Residential Complex: 92%
  • Phase II – Hospital and Academic Campus: 84%

5

Gorakhpur,

Uttar Pradesh

20.07.2016

1011

June, 2021

  • Progress of construction work: 78.9%

6

Bathinda,

Punjab.

27.07.2016

925

June, 2021

  • Progress of construction work: 78.75%

7

Guwahati,

Assam

24.05.2017

1123

June, 2022

  • Progress of construction work: 40.12%

8

Bilaspur, Himachal Pradesh

03.01.2018

1471.04

Dec, 2021

  • Progress of construction work: 54%

9

Madurai, Tamil Nadu

17.12.2018

1264

Sep, 2022

(Depends on JICA

collaboration)

  • Negotiation for loan from Japan International Co- operation Agency (JICA) completed.

10

Darbhanga, Bihar

15.09.2020

1264

Sep, 2024

  • Agency for Pre-investment activities appointed.
  • State Govt is required to handover 200 acre encumbrance free land which is still awaited.

11

Samba, Jammu,

Jammu & Kashmir

10.01.2019

1661

Jan, 2023

  • Progress of construction work: 10%

12

Awantipura, Kashmir,

Jammu & Kashmir

10.01.2019

1828

Jan, 2025

  • Progress of construction work: 3%

13

Deoghar,

Jharkhand

16.05.2018

1103

March, 2022

  • Progress of construction work: 30%.

14

Rajkot, Gujarat

10.01.2019

1195

Oct, 2022

  • Executing Agency for the main work appointed.
  • Design Consultant appointed.
  • Construction agency for the main work appointed.
  • Construction work started.

15

Bibinagar, Telangana

17.12.2018

1028

Sep, 2022

  • Agency for pre-investment work appointed.
  • Agency for the main work appointed.
  • Design Consultant appointed.

16

Manethi, Haryana

28.02.2019

1299

Feb, 2023

(Depends on getting encumbrance-free land from the State Govt.)

  • Encumbrance free land yet to be handed over by State Govt.

To view the official notice click on the following link:

https://medicaldialogues.in/pdf_upload/au3140-2-150715.pdf


Tags:    

Disclaimer: This website is primarily for healthcare professionals. The content here does not replace medical advice and should not be used as medical, diagnostic, endorsement, treatment, or prescription advice. Medical science evolves rapidly, and we strive to keep our information current. If you find any discrepancies, please contact us at corrections@medicaldialogues.in. Read our Correction Policy here. Nothing here should be used as a substitute for medical advice, diagnosis, or treatment. We do not endorse any healthcare advice that contradicts a physician's guidance. Use of this site is subject to our Terms of Use, Privacy Policy, and Advertisement Policy. For more details, read our Full Disclaimer here.

NOTE: Join us in combating medical misinformation. If you encounter a questionable health, medical, or medical education claim, email us at factcheck@medicaldialogues.in for evaluation.

Our comments section is governed by our Comments Policy . By posting comments at Medical Dialogues you automatically agree with our Comments Policy , Terms And Conditions and Privacy Policy .

Similar News