- Home
- Medical news & Guidelines
- Anesthesiology
- Cardiology and CTVS
- Critical Care
- Dentistry
- Dermatology
- Diabetes and Endocrinology
- ENT
- Gastroenterology
- Medicine
- Nephrology
- Neurology
- Obstretics-Gynaecology
- Oncology
- Ophthalmology
- Orthopaedics
- Pediatrics-Neonatology
- Psychiatry
- Pulmonology
- Radiology
- Surgery
- Urology
- Laboratory Medicine
- Diet
- Nursing
- Paramedical
- Physiotherapy
- Health news
- Fact Check
- Bone Health Fact Check
- Brain Health Fact Check
- Cancer Related Fact Check
- Child Care Fact Check
- Dental and oral health fact check
- Diabetes and metabolic health fact check
- Diet and Nutrition Fact Check
- Eye and ENT Care Fact Check
- Fitness fact check
- Gut health fact check
- Heart health fact check
- Kidney health fact check
- Medical education fact check
- Men's health fact check
- Respiratory fact check
- Skin and hair care fact check
- Vaccine and Immunization fact check
- Women's health fact check
- AYUSH
- State News
- Andaman and Nicobar Islands
- Andhra Pradesh
- Arunachal Pradesh
- Assam
- Bihar
- Chandigarh
- Chattisgarh
- Dadra and Nagar Haveli
- Daman and Diu
- Delhi
- Goa
- Gujarat
- Haryana
- Himachal Pradesh
- Jammu & Kashmir
- Jharkhand
- Karnataka
- Kerala
- Ladakh
- Lakshadweep
- Madhya Pradesh
- Maharashtra
- Manipur
- Meghalaya
- Mizoram
- Nagaland
- Odisha
- Puducherry
- Punjab
- Rajasthan
- Sikkim
- Tamil Nadu
- Telangana
- Tripura
- Uttar Pradesh
- Uttrakhand
- West Bengal
- Medical Education
- Industry
HC slams Delhi Govt for 'lethargy' in construction of 100-bedded Najafgarh hospital
The Court made it clear to the Delhi government that it cannot sit tight upon the matters asking it to follow the process of law keeping in mind the welfare of the public at large.
New Delhi: The Delhi High Court on Wednesday criticised the Delhi government for its "lethargic attitude" on processing the forest clearance required to complete a 100-bedded hospital in the Najafgarh area.
A Division Bench of Chief Justice DN Patel and Justice Jyoti Singh called it unfortunate of the public that a 100-bedded hospital in the Najafgarh area was not completed and criticized the Delhi government for showing a lethargic attitude in processing the forest clearance.
However, the Court granted time to the Delhi government to file its reply to the petition indicating the least possible time within which the state government may grant permission/sanction, as required by the Centre under law.
The Court also remarked that the Centre is writing letters after letters and no reply has been given by the Delhi Government, nor it file any counter-affidavit in the writ petition. The Court made it clear to the Delhi government that it cannot sit tight upon the matters asking it to follow the process of law-keeping in mind the welfare of the public at large.
The Court has listed the matter for hearing on November 8.
Also Read: ICMR Cannot Sit In Ivory Towers After Giving License To Private Labs: Delhi HC
The Court's remarks came while hearing the litigation filed in public interest filed by a lawyer Rajesh Kaushik, seeking a direction to the governments to complete construction and operation of the 100-bedded general hospital at the site of Rural Health Training Centre (RHTC) in Najafgarh here.
Henceforth, the Centre has urged the Delhi High Court to direct the concerned authority to expedite clearance for transplantation of trees so that the construction work at the RHTC Najafgarh, Delhi can be completed.
Representing the Centre, advocate Anurag Ahluwalia, told the Court that the physical progress of the construction work of the hospital is 80 per cent completed, except the peripheral road, pending for want of clearance from the Department of Forest, Ministry of Environment and Forest, Government of NCT of Delhi, for transplantation of trees.
The Centre government also apprised the Court that the hospital may be completed by the end of the year, subject to the clearance of pending approval by the Department of Forest, Ministry of Environment and Forest, Government of NCT of Delhi as clearance from Delhi government's forest department is pending since December 2018.
The Centre submitted that the work involves shifting/transplantation of few trees and the same could be undertaken only after the forest clearance is available. Henceforth, the Centre has urged the Delhi High Court to expedite clearance for transplantation of trees so that, the construction work at the RHTC Najafgarh, Delhi can be completed.
Farhat Nasim joined Medical Dialogue an Editor for the Business Section in 2017. She Covers all the updates in the Pharmaceutical field, Policy, Insurance, Business Healthcare, Medical News, Health News, Pharma News, Healthcare and Investment. She is a graduate of St.Xavier’s College Ranchi. She can be contacted at editorial@medicaldialogues.in Contact no. 011-43720751